Construction and development of an underground parking garage at the existing facility in Tortosa
Construction and development of an underground parking garage at the existing facility in Tortosa
Client:
Gestión de Infraestructuras, S.A. (GISA)
Location:
Tarragona
Type of work:
Specific
Architect:
Estudi Carme Pinós, S.L.P.
Construction and development of an underground parking garage at the existing facility in Tortosa
Construcción de un aparcamiento de tres plantas subterráneas con una superficie construida de 7.703,60 m2..
Demolition and Earthworks
- Demolition of phone booth and entryway.
- Excavate three stories of earth (18,976.53 m3).
Pouring a foundation
- Core walls 60 cm thick and between 17.90 and 19.95 m deep (3,996.72 m2).
- Shielded piles between 60 and 80 cm thick and 8, 10, 12, and 14 m deep (2,370.00 m2).
- 1.00 m thick foundation slab (2,841.19 m3).
Structure
- Reinforced concrete pillars (160.45 m3) and metal pillars (49,637.37 kg).
- Waffle slabs 7.5 + 25 + 7.5 (10,752.03 m2) and reinforced concrete slabs (2,340.45 m3).