Sidewalk maintenance, preservation, and improvement, and the Lleida rapid response team
Sidewalk maintenance, preservation, and improvement, and the Lleida rapid response team
This contract includes the maintenance, preservation, and improvement of sidewalks, roads, signage, and street furniture in the city of Lleida. In addition, a rapid response team is available to respond to emergencies 24 hours a day, 7 days a week.
Client:
Lleida Municipal Government
Location:
Lerida
Period:
2012
Type of work:
Other infrastructure
Budget:
€524,445.60 (excluding VAT)
Interventions performed:
Interventions on sidewalks and urban spaces
- Maintenance operations and repairs.
- Expansion of sidewalks.
Interventions on roadways
- Road surface repair with MBC.
- Partial repairs of asphalt paving.
- Road surface repair with concrete and paving stones.
Other interventions
DETAILS
Technical data
- Conservation works on sidewalks, roadways, signage and elements of street furniture.
- Availability of a rapid response team to respond to emergencies (24 hours a day, 7 days a week).
- 12-month execution period.