Installation of new pedestrian and bicycle routes for the creation of a Low Emission Zone on two avenues in Lleida


Installation of new pedestrian and bicycle routes for the creation of a Low Emission Zone on two avenues in Lleida

Urban planning intervention for the creation of a new Low Emission Zone (LEZ) in the municipality of Lleida.

Client:
Lleida Municipal Government
Location:
Lerida
Period:
2023
Type of work:
Roads and tunnels
Architect:
Sergio Gimeno Arribau

A Low Emission Zone (LEZ) requiring an urban planning intervention has been established in the area of Rambla Aragón at Plaza Cataluña at its junction with Calle Juan Baiget and Prat de la Riba between the junction of Alcalde Porqueres and Príncipe de Viana in the city of Lleida. 

The project is part of Intervention 2 – P6_L2-20210928-1. New services will be created and existing ones will be improved with the adaptation of a cycle lane and the widening of the pavement. In addition, the paving and landscaping elements will be renewed. 

The work is taking place in an urban environment with open vehicle and pedestrian traffic. 

In an initial phase, existing pavements and roads are demolished by partial traffic diversions, new services are built, existing services are repaired and replaced, and paving is carried out using pre-cast concrete (kerbs, gutters, cobblestones and hydraulic tiles to make the paths for the blind) combined with resin and aggregate-based finishes. For the latter, use is made of the Calcel Rob system and landscaping elements (both trees and shrubs). 

The main feature of this project is that it is a rainwater collection system, as the outer paving is made up of draining cobblestones and the Calcel Rob system. Another important feature is that all waste, both concrete and rubble from demolitions, is crushed and reused.

 
DETAILS

Technical data

Demolition of pre-cast concrete elements: 4,384 m³

Demolition of asphalt pavement: 5,689 m³

Crushed waste to be turned into recycled gravel: 1,109 m3

Draining gravel in sub-bases: 1,123 m3

Landscaped area: 1,524 m2

Concrete poured into slabs, paving, and grip for kerbs and gutters: 1,293.99 m3

Hot asphalt paving: 701 t

Draining cobblestone paving: 1,784 m2

Non-draining cobblestone paving: 1,709 m2

Calcel Rob paving: 558 m²